ANNUAL TOWN REPORT 2003
DEPARTMENT OF PUBLIC WORKS
To
the Residents of East Longmeadow:
The past year has once again been very busy and productive
for the Department. Outlined below
are some of the more significant accomplishments/occurrences that took place
during the year.
Sanitary & Stormwater Sewer Systems
Major
improvements to the town’s stormwater collection system were made at five
locations that include: Somers Road at house #91, Quarry Pond on Somers Road,
St. Josephs Drive, East Village Road, and Mountainview Road.
On
Mill Road a new catch basin was installed with discharge modifications at the
stream.
Department
personnel completed the new drainage system on Lee Street and the culvert at
Watchaug Brook was replaced. Lee
Street will be resurfaced during the coming summer.
There
are approximately 2,400 catch basins located around town that must be cleaned
of debris. With a fiscal year 2004
appropriation, we purchased catch basin cleaning equipment so our own personnel
can perform the cleaning, which was previously done by an outside
contractor. This will result in
considerable savings to the Town.
The
department responded to 79 plugged sewer calls in addition to the regular
cleaning and maintenance of the sanitary sewer system.
The
stormwater detention basin in the Evergreen Drive neighborhood was refurbished.
Construction
continues on the replacement of the Vineland Avenue sanitary sewer pumping
station. This facility is
responsible for the transfer of the majority of the town’s wastewater to
the Bondi Island Treatment Plant.
It is scheduled to go on line in February.
Work
has been completed on a deteriorated section of sanitary sewer main that
crosses Pecousic Brook behind Rocky’s Hardware store.
Resulting
from resident petitions, the department extended the sanitary sewer mains on
Athens Street and on Redstone Drive.
Water System
The
department continues to make improvements to the drinking water distribution
system. The water mains were
replaced on Meadowbrook Road, Smith Avenue, Lee Street, Lombard Avenue,
Roderick Avenue, Lyric Avenue, a section of Vineland Avenue, and Parker Street
from Meadowbrook Road to Porter Road.
This work was performed by outside contractors by applying funds from
Warrant Articles and the Water Revolving Fund. These improvements will greatly increase
the amount of water flow available to fight a fire and also improve water
quality and system reliability.
There were 19 major water main breaks throughout the year, which were
repaired by this department.
Due to changing state and federal environmental
regulations, the DPW has been designing a computerized alarm and control system
to be installed at all of our water and sewerage pump stations. Work is continuing on our SCADA
(supervisory control and data acquisition) system and should be completed
soon. As each station becomes
operational, the ability to monitor and control these facilities becomes
possible from remote locations, such as the Public Works office in the Town
Hall. The SCADA system will increase
productivity and accuracy in our daily work.
The Department is
currently replacing the “visual read” water meters with
“radio read” meters.
These new style meters have a radio transmitter attached to them, which
broadcasts a signal. Once the entire
town is converted, the method of reading the meters will be to simply drive
down the street with the receiver in the vehicle. After capturing the readings, the
receiver will be returned to the office.
Downloading of the readings will be done by a direct connection between
the receiver and the computer billing system. No manual entry will be necessary.
Advantages
of “radio read” meters include:
- Faster meter reading
- Greater accuracy
- Increased operator
safety
- Fewer re-reads
- Elimination of
hard-to-read meters
- Tamper detection
- Improved customer
service
In
January of 2004, we will be going to quarterly water/sewer billing. Advantages include:
- Improved cash flow
- Smaller payments for
customers
- Quicker detection of
customer “excessive usage”
Highways & Parks/Grounds
We
are continuing working towards the construction of a bike trail that will run
along the old railroad bed from Denslow Road to Maple Street. Funding for this project is from a
“State” grant. A new
sanitary sewer force main will also be installed at this location. We have purchased two land parcels and
are currently negotiating for easement rights on the remaining parcel.
Through
a joint effort between the Board of Selectmen, Recreation Department, Police
Department, and Department of Public Works, a set of Park Rules was
established to assist us in the maintenance and management of our parks and
playgrounds.
The
infields at the two baseball/softball fields at Birchland Park School were
completely rebuilt by the department.
At
Baba Park, the department replaced the playground equipment.
At
Heritage Park a new fire hydrant was installed. Besides providing additional fire
protection, it will be used to flood the pond for recreational ice-skating.
In an effort to reduce insurance premiums, smoke/fire
detectors, which report to the Fire Department, were installed at the Service
Building on Somers Road.
With
a capital appropriation, the department purchased a “tub”
grinder. This equipment is used to
grind all brush and trimmings that are brought to the Transfer Station, thus
eliminating our need to pay for outside disposal charges.
Chestnut Street between Somers Road and Prospect Street
was resurfaced. The entire length
of Westwood Avenue was repaved this year.
Major roadway improvements are needed on Allen Street from
Tanglewood Drive to the Hampden Town Line. With a fiscal year 2004
appropriation we received, preliminary designs are under way and will be
submitted to the Massachusetts Highway Department for their review. Several streets, including Elm Street,
Allen Street, Mapleshade Avenue and Westwood Avenue are on the States
Transportation Improvement Project (TIP) list for improvements. Modifications include road
reconstruction, sidewalk and drainage installation. We are still awaiting approval of these
projects.
Progress continues with the department’s
participation with the Geographical Information System (GIS). Tighe & Bond, our consulting
engineers on this project, has been working on securing the services of an
aerial photography company to proceed with the “flyover” of the
Town in late March or early April of 2004.
The
department received $292,153 in Chapter 90 funding.
Personnel
Throughout
the year, members of the Fire Department gave “CPR” and
“Hazardous Material” training courses to our employees. We would like to offer Chief Wallace and
his staff our sincere thanks for their continued assistance and
inter-departmental cooperation.
One
retirement occurred during the year, namely, Ely Christenson, with 40 years of
service. Our gratitude and best wishes go out to Ely.
Three
employees resigned during the year:
- Walter Henry
- Melvin Cosme
- David Vautrain
There
were three new hires to fill vacancies:
- Kevin Quick –
Skilled Worker
- Neil Von Flatern
– Skilled Worker
- Steven Moore –
Mechanic
We
would like to express our appreciation to the dedicated members of the East
Longmeadow Garden Club and the East Longmeadow Jaycee’s for their
volunteer work.
In
closing, the Board of Public Works would like to thank its staff as well as the
other Town boards, departments, and committees for there continued cooperation
and assistance.
Respectfully
submitted,
John
F. Maybury, Chairman
Daniel
S. Burack
Michael
A. Perkins