ANNUAL TOWN REPORT 2005
DEPARTMENT OF PUBLIC WORKS
To the Residents of East
Longmeadow:
Outlined below are some of
the more significant accomplishments/occurrences that took place during the
year.
Sanitary & Stormwater Sewer Systems
Watchaug
Brook Force Main Replacement Project: This project involves the replacement of
an existing 12" asbestos cement force main with a new 12" DI/PVC
force main between the Watchaug Brook Sewage Pump Station and the United
Methodist Church on Somers Road. Contract #1 (on Somers Road from Michel
Street to the church) was constructed during the fall.
Mill Road
Sanitary Sewer Project: This project involved the extension of a gravity sewer
main along Mill Road from Meadowbrook Road to the Hampden Town line. The
project was completed in December.
The
department responded to 22 plugged sewer calls in addition to the regular
cleaning and maintenance of the sanitary sewer system.
Shaker Road
Sewer Replacement Project: This project involved the extension of the Denslow
Force Main from Chestnut Street to Maple Street, along the existing railroad
easement to relieve capacity issues within the existing sanitary sewer on
Shaker Road. This project was completed during the summer.
Denslow Road Pump Station Improvements Project (Contract
#2): In conjunction with the Shaker Road Sewer Replacement Project (a.k.a.
Denslow Force Main Extension, a.k.a. Bike Trail Sewer), this project involves
the upgrade of the station's mechanical components including pumps, piping,
stand-by power provisions and electrical/control upgrades. This project is out
to bid for late January 2006 contract awarding.
Pease Road
Reconstruction: This project involves the extension of the gravity sewer on
Pease Road from Old Farm Road to Prospect Street, highway reconstruction and
storm drainage improvements. Work is scheduled for early summer of 2006.
At the High
School, a new gravity sanitary sewer main was installed between the school and
Barrie Road thus eliminating the need for a pumping system.
Water System
The drinking water disinfection system at
the Chestnut Street Pumping Station was modified. Disinfection has been
changed from chlorine to chloramine. Chloramine disinfection will provide for
effective deactivation of bacteria and other water-borne microorganisms.
New water mains were
installed on Peachtree Road, Windsor Lane, Canterbury Circle, Rockingham
Circle, Dell Street, Fenway Lane and Deer Park Drive. There were 18 major
water main breaks throughout the year, which were repaired by this department.
New Water Tank Replacement
Project: An additional 2,000,000-gallon water storage tank is being designed
for the Prospect Street site. Contract #1 which was for a new underground pipe
network for the new tank has been completed. Contract #2 has been awarded for
the demolition of the existing 75,000-gallon tank. This work will occur in
early 2006. Contract #3 is for the construction of the new tank and will be
put out to bid after the first of the year.
Highways & Parks/Grounds
Resurfacing
occurred on the following streets: Maple Street, Chestnut Street, Pleasant
Street, Pease Road, Calkins Avenue, Murray Court, Newbury Avenue, Alpine
Avenue, Veranda Avenue, Greenacre Lane and Merriam Street. Allen Street was
repaved from Porter Road to the Hampden Town Line. Highway 'crack sealing' was
performed on sections of Hampden Road and Chestnut Street.
Synchronization
of the traffic signal lights on North Main Street from Harkness Avenue to
Mapleshade Avenue was completed. Various signal lights and control systems
were replaced and a more effective synchronization scheme was implemented at
the intersections.
At Heritage
Park, both baseball fields were completely rebuilt. The fields were re-graded
to comply with athletic field specifications, irrigation systems installed, and
covered with turf. Leahy baseball field also underwent major repairs.
Department personnel did all work.
The Department, made
further updates to the Heritage Park Playground with additional funding
contributed by the Friends of Heritage Park.
Through a Capital
appropriation, the department replaced a front-end loader and a backhoe.
The Department continued
work on the installation of the underground fiber optic system. The new fiber
optic system will allow for almost instant communication between sites and
allow for ultra-high speed internet access. The Department's water and major
sanitary sewer pumping stations are now connected via fiber optics to our SCADA
system that allows for optimal operation of the facilities.
As a result of the
record-breaking rains in early October, the Public Works crews worked around
the clock to keep our town roads open. After receiving more than 15 inches of
rain in one week, culverts on Prospect Street, Meadowbrook Road, Pease Road,
Mapleshade Ave, Elm Street, and others, overflowed and were washed out.
Additionally, crews tended to flooded sanitary sewer pump stations and assisted
the fire department in pumping out resident's basements.
Building Facilities Maintenance Division
During the past year, the
Building Facilities Division has managed the following School Capital projects:
Meadowbrook
School:
Bathroom
renovations: ADA accessible doors, toilet partitions, upgraded lighting and
plumbing fixtures, tile flooring, and painting.
Mountainview
School:
Addressable
Fire Alarm System: Coordinated
the installation of an Analog Fully Addressable Fire Alarm System.
High
School:
Pool
renovations: Painting, tile repairs, ceiling tiles, etc.
Front
Doors: Replaced front entrance doors and installed a handicapped entrance
opener.
Gymnasium
Dividers: Replaced existing gymnasium dividers.
Hall
Fire Doors: Added magnetic door holds and wiring to complete Fire Alarm System
for hall doors.
Bleachers:
Coordinated the effort to ascertain bleachers for the Football Field.
Mapleshade
School:
Addressable
Fire Alarm System: Coordinated the installation of an Analog Fully Addressable
Fire Alarm System.
Intercom
System: Replaced existing system with a phone intercom system.
In addition to managing
school capital projects, the building facilities division has completed
renovations to the Town Hall utilizing Public Works staff in conjunction with
various subcontractors. The renovations included: Gutter replacement,
painting, carpet replacement, heating duct cleaning, HVAC upgrades, electrical
upgrades, lighting improvements, ceiling replacements, security system
upgrades, installation of a central fire alarm system, and other interior
renovations. A third floor storage space was created above the existing DPW
offices as well as basement shelving to help fill the current need for file and
plan storage.
This division has also
managed the day-to-day maintenance for all Town buildings and developed and
implemented a self-inspection program that focuses on maintaining current
buildings to an acceptable standard thus eliminating unnecessary capital
projects. In an ongoing effort to curb expenses, this department has worked
closely with the Capital Planning Committee and the School Department to consolidate
projects Town wide.
Rich Gale, Building
Facilities Manager, has attended numerous courses and seminars which include:
Asbestos Awareness Training, Procurement training, HVAC maintenance classes,
and several MIIA training seminars.
At the East Longmeadow Fire Station, a new methane gas
extraction system was installed to mitigate high methane gas levels that were
detected inside the building in 2004. This system was installed during the
2004-2005 winter and has been in operation since. Sean Kelley, Senior Project
Manager played an integral part in the design and construction of this
endeavor.
Through negotiations with the Massachusetts Department of
Environmental Protection, the grass and leaves that we collect at the Knowlton
Transfer Station during the year, are transported to the former Allen Street
Landfill where they are using as 'capping' material. This results in decreased
disposal charges.
Construction of the Redstone Rail Trail (Bicycle and
Pedestrian) should be put out to bid during calendar year 2006 with
construction following shortly thereafter. Design plans are at 95% review
status with the Massachusetts Highway Department. On October 5th, 2005, U.S.
Congressman Richard Neal presented Public Works Officials with ceremonial check
in the amount of $1.44 million dollars representing federal funding awarded to
East Longmeadow for construction purposes. The Rail Trail is envisioned as a
multi-use trail designed to improve local recreation and transportation
opportunities for people of all ages and interests. The project will also
offer residents and visitors the opportunity to discover East Longmeadow's rich
history as a quarry town. The East Longmeadow High School has direct access to
the trail from its athletic fields providing opportunities for students to
study habitat for wildlife and native vegetation. The presentation of the
check culminated fourteen years of meetings, grant writing and lobbying by
members of the Redstone Trailway Committee and the Board of Public Works.
Personnel/Miscellaneous
Department staff attended
CPR and First Aid training during the year as well as continuing education
courses for those individuals who possess Massachusetts Drinking Water
licenses.
Fiscal Year 2006 budgeting
constraints resulted in the elimination of one skilled worker position from the
department. This loss is most evident during snow plowing operations. It must
be remembered that East Longmeadow, unlike most communities, does not use any
outside contracted assistance for snow plowing; all work is done by
departmental staff and equipment.
To fill a
vacancy in staff, Mr. William Ferraro was hired as a skilled worker.
In closing,
the Board of Public Works would like to thank its staff as well as the other
Town boards, departments and committees, and clubs and organizations for their
continued cooperation and assistance.
Respectfully
submitted,
Michael A.
Perkins, Chairman
John F.
Maybury
Daniel S.
Burack