ANNUAL TOWN REPORT 2006
DEPARTMENT OF PUBLIC WORKS
To the Residents of East Longmeadow:
Outlined below are some of the more significant
accomplishments/occurrences that took place during the year.
Sanitary & Stormwater Sewer Systems
Watchaug Brook Force Main
Replacement Project: This project involved the replacement of an existing
12" asbestos cement force main with a new 12" DI/PVC force main
between the Watchaug Brook Sewage Pump Station and the United Methodist Church
on Somers Road. The entire project is now completed.
The department responded to
41 plugged sewer calls in addition to the regular cleaning and maintenance of
the sanitary sewer system.
Denslow
Road Pump Station Improvements: This project involved the upgrade of the
station's mechanical components including pumps, piping, stand-by power
provisions and electrical/control upgrades. An odor
control system was also installed which utilizes a nitrate based liquid
chemical that is injected into the wastewater to reduce odors and hydrogen sulfide
at the force main discharge.
This
fall the Department took to task the clearing of the sanitary sewer easements
that run cross-country in many sections of the town. The removal of vegetation
and trees from these right-of-ways, which has not been done for many years,
allows our workforce access to sewer mains when emergency repairs are required.
Water System
There were 20 major water main breaks throughout the year,
which were repaired by this department.
New Water Tank Replacement Project: Construction began on
the installation of a new 2,000,000-gallon water storage tank on Prospect
Street. The underground pipe network for the new tank has been completed and
the old 75,000-gallon tank has been demolished. The foundation for the new
tank is in place with scheduled completion for next year.
During the past four years we have been replacing
manual-read water meters with new radio-read meters. These new type meters
allow us to read them simply by riding down the street. The readings are transmitted
by radio waves from the water meter and captured on a laptop computer inside
the vehicle. The reading of meters for a particular billing period can now be
accomplished in a matter of hours instead of weeks. By July 1st of
next year, the water meter conversion will be nearly complete.
In December, the Massachusetts Department of Environmental
Protection conducted a sanitary survey of the Town’s drinking water system. A
sanitary survey, which is conducted every four years, is an on-site review of our
water sources, facilities, equipment, operation and maintenance of our public
water system for the purpose of evaluating our system’s ability to produce and
distribute safe drinking water. We are pleased to report that no major
deficiencies were found in our system.
Highways & Parks/Grounds
Resurfacing occurred on the
following streets: Maple Street, Rollins Drive, Pease Road, Mill Road and a
section of Somers Road. The Police Department parking lot was also resurfaced.
The Department, working in conjunction with the East
Longmeadow Jaycees, made further improvements to Heritage Park. The old “skate
shack” was removed and rebuilt. The new facility has been fitted with
electrical power and an area that can be used for concessions.
The Department continued work on the installation of the
underground fiber optic system. The new fiber optic system provides for almost
instant communication between sites and allows for ultra-high speed internet
access. We are now looking to expand the network to provide service for both
residential and commercial use.
Building Facilities Maintenance Division
Rich Gale, the Town’s first
Building Facilities Manager, resigned in June to pursue a career in the private
sector. He was instrumental in establishing the new Building Facilities
Division in the Department and oversaw many improvements to Town buildings
during his tenure. In July, Mr. Bruce Fenney was hired to succeed Rich.
During the past year, the Building Facilities Division has
managed the following Capital projects:
Meadowbrook School:
Install
new ADA hardware on all interior doors.
Electrical upgrades in all
classrooms.
Mountainview School:
Electrical upgrades in all
classrooms.
High School:
Replace
9x9 asbestos tile with VCT tile in South Wing.
Auditorium Rigging replaced and
asbestos fire curtain removed.
Mapleshade School:
ADA
Bathroom Renovations: ADA doors, toilet partitions, plumbing fixtures.
Replace
67 windows in north and south wing hallways.
Replace
four gymnasium exterior doors.
Install
new compressor for pneumatic control system.
Install
new emergency lighting throughout building.
Repair heating system entire
building: steam traps, repair old pipe in tunnels, vacuum return system.
Town Hall:
Installed
new Leibert Challenger 3000 Environmental Control System in the town’s server
room.
Install
new heating diffusers with thermostats in four offices on first floor.
Police Station:
Paint
interior of building first and second floor plus garages.
Install
new carpet throughout entire facility.
Strip
and wax existing floors throughout building.
DPW Service Building:
Install
vehicle wash platform.
Personnel/Miscellaneous
The Redstone Rail Trail
Project is finally advancing towards fruition. The final plans have reached
the 100% phase and Mass Highway has approved the plans for construction. Final
negotiations with Hasbro for use of a portion of their property are almost
complete. It is anticipated that the project will be put out to bid by the
State during the late spring of 2007 and construction could start soon after.
The two closed landfills
currently under the jurisdiction of the Board of Public Works have been
continuously monitored for leachate of hazardous materials. Both the Allen
Street site and the Knowlton Transfer Station are currently being utilized for
our composting operations. The Department of Public Works has developed a
composting program that uses all of the grass and leaf waste from the Transfer
Station and turns it into dark topsoil. This mulched topsoil is then added to
screened loam and will save the Town monies normally spent towards loaming tree
belts and the like.
The Knowlton Transfer Station
was open 86 days last year and took in over five thousand tons of refuse. The
Transfer Station currently accepts yard waste, brush, metal items, wood items,
used motor oil, fluorescent bulbs and mercury containing items and for a
nominal charge, bulk items. The Transfer Station is open Saturdays year round
(9am to 5pm) and Wednesdays seasonally (mid-April through November).
Department staff attended CPR and First Aid training
during the year as well as continuing education courses for those individuals
who possess Massachusetts Drinking Water licenses.
In October, Secretary Kathy Field passed away after
battling cancer. We all miss Kathy’s wit and good humor.
Two retirements occurred
during the year. We extend our thanks and congratulations to these longtime
and dedicated individuals.
· Derwood Pepoon - 19 years of
service
· Stanley Obara - 14 years of
service
Two employees resigned during the year:
There were six new hires to
fill vacancies:
- Bruce
Fenney – Building Facilities Manager
- Cori
Savio – Secretary
- Dennis
Olisky – Skilled Worker
- Stephen
Monette – Skilled Worker
- Michael
Hill – Custodian
- Linda
Zebrowski – Custodian
Promotions:
- Michael
Ciepiela to Building Facilities Technician
- Erich
Rasid to Equipment Operator
In closing, the Board of
Public Works would like to thank its staff as well as the other Town boards,
departments and committees, and clubs and organizations for their continued
cooperation and assistance.
Respectfully submitted,
John F. Maybury, Chairman
Daniel S. Burack
Michael A. Perkins